At SES we are constantly pushing the boundary with each new project, in order to add value to our clients. The projects we have undertaken continue to cut across a wide spectrum of sectors.

  • Completed Projects

S/NO.

CONTRACT DESCRIPTION

39

Spares and overhaul of 2 CAT engines---OES.

38

Replace cylinder liners, connecting rod bearings, piston rings, piston assembly, cylinder head assemblies for compressors--- OES

37

Spare parts purchasing and 8000 hours maintenance overhaul of Akondo gas lift compressors --- ADDAX

36

Overhaul (48 000 hours) Ariel JGE/4 F-24782-273-3063 compressor (Maintenance and replacement of compressor cylinders, valves, lubricants, etc.)---ADDAX

35

Installation & Commissioning Of PAGA Control System PLC ,ANYALA WEST/FPSO

34

OKI-OZIENGBE-OREDO Metering Station Upgrade

33

Instrumentation & Electrical works on the SPM for the Escravos Export System Project

(EESP-2020- CW1794619) 

32

Pre-commissioning/ Commissioning of 36”x 55KM Dangote Fertilizer Gas transportation

31

Routine pigging of 12” x 23km Imo River 1 /Oghale trunk line

30

Routine pigging of 12” x 4 km from Oghale to Ebubu Delivery line

29

Routine pigging using Auxiliary Pumping of 24” x 52 km Oghale/Bonny TMP

28

Routine pigging using Auxiliary Pumping of 8” x 9.8 km Isi-Mmiri /Imo gate delivery line

27

Routine pigging of 12” x 23km Imo River 1 /Oghale trunk line

26

Routine pigging of 8” x 3km Agbada 1 & 2  Delivery line

25

Escravos Export System Project, Terminal Piping scope

24

Engineering/Procurement/Construction

of Drain Drum vessel

23

Construction Of Temporary refuge

22

Engineering/Procurement/Construction

Of Pig launchers & Receivers

21

24’’ Valve maintenance at NGC Flow station at Owasa

20

Addax SCS Upgrade system

19

Pre-commissioning/ Commissioning of 24”x 56KM Escravos Node-WGTP Gas Transportation Pipeline

18

Pre-commissioning/ Commissioning of Expansion Of Escravos Lagos pipeline System Phase II Project

(36”x97 km pipeline, PS 1-PS 2)

16

Pre-commissioning/ Commissioning of 24”x 56KM Escravos Node-WGTP Gas Transportation Pipeline

15

Front End Engineering Design, Detailed Engineering Design of Gas Compressor complete with PLC control systems.

14

 

 

Pre-commissioning of 30” x 6.07km Gas pipeline. EESP

Location:  from Escravos Terminal to Offshore tie in point “Costain”

13

Pipeline pigging, removal of condescend from a 18” x 5km Gas Pipeline.

Location:  from IPS Aloji Aba to Gas metering Station Aloji.

12

Pre-commissioning of 12” x 8.5km Gas Pipeline.

 

Location:  from AGI Trans-Amadi to BUA Factory opposite Spar PHC

11

Pre-commissioning of 4” x 2km Flow line.

Location:  AGIP Kwale flow line Beniku.

10

Pre-commissioning of 24” x 56km Gas Pipeline.

 

Location:  from NGC base warri to Escravos Node.

09

12” x 45km offshore export pipeline pigging & Hydrotest.

Location: Agbani Abana East to KAD). Offshore.

08

Pre-commissioning of different sizes of pipe spools for Egbema power plant metering station.

Location: Egbema metering station.

07

Pre-commissioning of 24” x 56 km gas pipeline

Location: from NGC base warri. To Escravos Node

 

06

18” X 2.5KM pipeline cleaning and hydrotest

Location: Soku Gas plant  to Soku flow station. Swamp

05

Agbani Barge HVAC Change-Out and Upgrade.

 

Location: Agbani Barge, Offshore

04

6” X 8.5KM Ebendo Export line stuck pig removal, installation of pig Launcher and 6” full bore ball valve.

Location: Kwale 

03

Pig Signal Indicator Services, maintenance and installation

Location: Abana East/

Knock Adoon. Offshore

02

Coarse Strainer Change Out & Installation

01

Third Stage Separator change out / installation

Location: Abana East/Knock Adoon